  • 10th Jan 2018 – Work completed on site till date
    • Level work completed
    • Alignment of roads completed
    • Demarcation of plots completed
    • Boundary wall work in progress
  • Forest and Pollution clearances in hand.
  • Loan partners – SBI , ICICI.
  • 28th sept –RERA Approved.
  • Maruti Kunj by Sadaa - The first authorized gated plotted township of Farukhnagar.
  • 16th May - Work commenced on site.